$15 million plant to increase energy efficiency, resiliency at medical center

May 15, 2017

Boston Medical Center is now generating much of its own electricity and heat through a natural gas-fired, 2-megawatt combined heat and power plant (CHP, or cogen), further enhancing the facility’s standing as the most resilient and greenest hospital in Boston, according to a release. 

The cogen facility – about the size of a tractor trailer – will save BMC about $1.5 million in heat and energy costs annually, officials said. Traditional power plants, which release excess heat into the atmosphere, operate at about 35 percent efficiency. Cogen technology, which instead traps and reuses the heat, operates at 70 percent efficiency.

“Increasing efficiency and resiliency makes financial and operational sense,” hospital CEO and President Kate Walsh said. “Cogen will save about $1.5 million in energy and heating costs, which are resources we can spend on patient care, instead of utility bills.”

BMC is the only major teaching hospital in Massachusetts that currently has “black start” capability, meaning that if the electric grid goes down, the hospital can restart the cogen plant and heat and power its inpatient units on an “island” for months at a time, as long as it has a supply of natural gas. The cogen plant, which became operational this spring, is also on the roof of the Yawkey Ambulatory Care Center, high above any potential floodwater.

“We’ve learned lessons from Hurricane Katrina and Sandy, which devastated the health care infrastructure in their communities,” said Bob Biggio, senior vice president for facilities and support services. “Hospitals that had cogen were able to stay open and care for patients, while those without cogen were forced to evacuate. As the largest safety-net hospital and biggest trauma center in New England, we have an obligation to protect our patients in a natural disaster. Cogen gives us the ability to continue to care for the most vulnerable population in our city, even when the electric grid goes down.”

The $15 million cogen plant was made possible by a $3.7 million grant from the Massachusetts Department of Energy Resources’ Community Clean Energy Resiliency Initiative. The Boston Public Health Commission partnered with BMC in securing the grant. In addition to powering and heating much of the hospital, the cogen facility will also serve as a backup power source for city and state emergency communications.

Eversource provided BMC with financial incentives to bring cogen to the hospital campus. In the last four years, Eversource and BMC have partnered on more than 30 efficiency projects, achieving more than 8 million kilowatt hours in annual energy savings, or roughly 5 percent of the hospital’s total electricity usage. The hospital has also avoided more than 5,600 metric tons of carbon dioxide emissions each year through its comprehensive energy strategy with Eversource, which is the equivalent of removing 1,200 cars from the road. 

The cogen plant, manufactured by Caterpillar and designed by Engineered Solutions, will supply more than 41 percent of the hospital’s electricity and has the capacity to meet 25 percent of peak electricity demand at any given time.

By reusing the trapped heat for hot water, humidification and room temperature, the hospital will lower costs by reducing its need for steam heat by an estimated 44,000 pounds annually. Cogen will also reduce electric grid consumption by more than 16 million kilowatt hours a year.

The hospital has taken other important steps toward resiliency: Installing new generators on floors of patient care buildings; creating cross-building critical infrastructure connections, so when one patient building loses power, it can connect to the generator in an adjacent building; and programming elevators to stop short of the lower floors to maintain patient care in the event of a flood.

BMC, which was already cutting emissions by 50 percent as part of a clinical campus redesign, also announced a solar power purchase agreement last fall with MIT and the Post Office Square Redevelopment Corporation. The solar purchase is equivalent to 100 percent of BMC’s projected electricity consumption, making BMC the greenest hospital in Boston and on pace to become the first carbon-neutral hospital in New England upon completion of the campus redesign in 2018.


Topics: Architectural Firms, Automation and Controls, Building Owners and Managers, Construction Firms, Consulting - Green & Sustainable Strategies and Solutions, Energy Saving Products, Engineering Firms, Exteriors, Great Commercial Buildings, Healthcare - Hospitals & Medical Facilities, Healthy & Comfortable Buildings, HVAC - Heating, Cooling, and Ventilation, Indoor Air Quality (IAQ), Sustainable Communities, Technology, Urban Planning and Design, Utility and Power Plants


Sponsored Links:


Related Content


Latest Content

Get the latest news & insights


NEWS

RESOURCES

TRENDING

FEATURES

RESEARCH CENTERS